# Can I start Multiple Sprint for a Scrum Project ?

> Currently, you can only view one sprint report at a time. And we're working on bringing multiple reports viewing to you soon.

> For the complete documentation index, see [llms.txt](https://helpdesk.orangescrum.com/llms.txt).

Source: https://helpdesk.orangescrum.com/can-i-view-the-reports-of-multiple-sprints-at-one-time

---
In order to start multiple sprints for a Scrum project, you need to enable Parallel sprints. You can do this by following below steps-

1.  Click on **Profile icon> Company setting>Sprint setting**.
2.  Click ![Enable sprint](https://helpdesk.orangescrum.com/images/help/2018/09/Enable-sprint.png) to the icon to enable parallel sprint and Click **Save.**

Once you have enabled the above option, you will be able to find sprint drop-down in the active sprints and you can select the required sprint you wan to see.

![Active sprints](https://helpdesk.orangescrum.com/images/help/2018/09/Active-sprints.png)