You can convert parent task to subtask and vice versa seamlessly.  Here is how you can do so-

**Convert Tasks to Subtask-**

-   Navigate to task list of the specific project.
-   Click on 3-dot icon of the specific parent task for which you want to convert to subtasks. Further click on **Convert to Subtask**. If you are unable to find the option, then there should be the Subsub tasks associated with it.

![sub-tasks to parent tasks](https://helpdesk.orangescrum.com/images/help/2020/10/Convert-Tasks-to-Subtask.jpg)

-   In the Convert to Subtask popup, select the parent for which you want the associated task as Subtask. Please note that, you will be able to find Tasks & Subtasks only in that menu.

![sub-tasks to parent tasks](https://helpdesk.orangescrum.com/images/help/2020/10/Convert-Tasks-to-Subtask-2.jpg)

-   Select the specific task or subtask and select save. Once saved, the specific task will be added as Subtask.

**Convert Sub-task to Task-**

-   Navigate to task list of the specific project.
-   Click on 3-dot icon of the specific Sub-task or Sub sub task and select Convert to parent. You can find that option for Subtasks and Sub sub tasks only.

![sub-tasks to parent tasks](https://helpdesk.orangescrum.com/images/help/2020/10/Convert-Sub-task-to-Task-1.jpg)

-   Once clicked, you will be asked for the confirmation about the change. Click OK on the alert box.
-   The sub-task or sub sub task will be detached from existing parent and become a normal task.