# How to Use the Gantt Chart for My Projects?

> Learn how to utilize the Gantt Chart in Orangescrum to plan, visualize, and manage your projects efficiently.

> For the complete documentation index, see [llms.txt](https://helpdesk.orangescrum.com/llms.txt).

Source: https://helpdesk.orangescrum.com/how-to-use-the-gantt-chart-view-for-my-projects

---
1.  On the left panel, click **More** \>**Gantt** chart option.
2.  You can also go to **+Quick links> Gantt chart**
3.  Select the respective ‘Project’, from the top Project drop-down menu once you are in the Gantt View.

![Gantt Chart](/images/help/2019/04/Gantt-chart.png "Gantt Chart")

#### **Who can View the Gantt Chart?**

Only the owner and admins can view the Gantt chart. If you need to provide permission to specific users, then you can do so by navigating [**User role management** **settings**](https://helpdesk.orangescrum.com/?post_type=post&p=6909).

#### **How can I Create Task Dependencies?**

1.  Choose your project from the drop down menu in header > Navigate to ‘Gantt Chart’ from the left menu.
2.  Hover on a taskbar at the beginning or the end. You can find two circles on both the ends.
3.  Click on one of the circle  & drag an arrow to another task bar you wish to link with.

![Gantt](https://helpdesk.orangescrum.com/images/help/2016/03/Gantt.png)

#### **How to Delete Dependency in Task?**

1\. Go to +Quick links> Gantt chart

2\. Double-click on the dependency you’d like to delete > Click ‘OK’ on the pop-up > Click Save Icon from the header menu of the Gantt view.