Can I generate Sprint burndown charts in Orangescrum?
Follow the steps below:
1.Login to orangescrum.
2.Click on the report from the left menu.
3.Scroll down and click on the sprint burndown report.

(Image-1)
4. Select a scrum project.
5. Select a sprint under the project.
6. The sprint Burndown report will be shown.

(Image-2)