For AI agents: a documentation index is available at /llms.txt. A markdown version of this page is available at /can-link-tasks-dependent.md.
How can I Link Tasks that are Dependent?
- Log in to your OrangeScrum account using your current credentials.
- Navigate to Left Menu >More>Gantt Chart
- Hover on the Task Block
- Click
icon & Drag it to one end of the child task (Refer Image 1)

(Image 1)