CloudTime & resources

Resource management

See who is committed to what, spot overload before it happens, and plan capacity honestly.

Premium Unlimited

Resource management, availability and utilisation are Premium features. Basic workload management is available on Pro.

Resource management answers three questions: who is available, who is overloaded, and can we take this on?

#Allocation

Assign people to projects with a percentage of their time and a date range โ€” "Priya, 50% on Website Redesign, March to May".

Allocation is a plan, not a fact

What people are allocated to and what they actually work on diverge. Compare allocation against logged time regularly, or you are planning against fiction.

#Availability

Capacity minus commitments minus absence. Feeds:

๐Ÿค”Can we take this on?

Real available hours in the window, not a hopeful guess.

๐Ÿ™‹Who can help?

Who genuinely has room this week.

๐Ÿ“…When can we start?

The earliest date the right people are free.

๐ŸšจWho is drowning?

Over-allocation, visible before it becomes a missed deadline.

#Utilisation

Booked or logged time as a percentage of capacity. Useful, and very easy to misuse.

100% utilisation is a broken system, not a good one

A team booked to 100% has no capacity to absorb anything โ€” a sick day, an incident, a task that turns out harder than expected. Everything becomes late the moment reality intrudes. Sustainable planning sits around 70โ€“80%.

The remaining 20โ€“30% is not waste. It is meetings, code review, helping colleagues, learning, and the buffer that lets a plan survive contact with the week.

#Planning honestly

  1. Start from real capacity

    Subtract holidays, public holidays, known absence, and standing meetings. What is left is what you can plan.

  2. Plan to 70โ€“80%

    Not 100%. The gap is what absorbs the unexpected.

  3. Check for over-allocation

    Someone at 130% across three projects will miss on all three, and each project manager will think they were unlucky.

  4. Reconcile with actuals

    Monthly, compare allocation to logged time. Adjust the plan to reality rather than insisting reality was wrong.

#Over-allocation

The most common and most damaging problem, because each project sees only its own slice.

Spot it early

The availability view shows total commitment across every project. This is the only place over-allocation is visible.

Fix it by deciding, not by hoping

Something must give: move a date, reduce scope, or reassign. Splitting someone across four projects and hoping is the option that always fails.

Watch context switching

Someone at 25% on four projects is far less productive than someone at 100% on one. The percentages add up; the productivity does not.

#Skills and matching

Availability is necessary but not sufficient โ€” the available person also has to be able to do the work. Record skills so the answer to "who is free?" is not someone who cannot take it on.

#Reporting

Utilisation, allocation and availability roll into the advanced dashboards, across projects and programs.