For AI agents: a documentation index is available at /llms.txt. A markdown version of this page is available at /guide/cloud/views/milestones.md.

CloudViews & boards

Milestones

Mark the delivery points that matter and track everything hanging off them.

A milestone is a dated point a project must reach โ€” a release, a client demo, a regulatory deadline. Tasks are assigned to milestones so you can see what is outstanding for each.

Available on every tier, including the Community Edition.

#What makes a good milestone

๐ŸŽฏExternally meaningful

Something a stakeholder would recognise: "Beta launch", "Client sign-off".

๐Ÿ“…Has a real date

A milestone without a date is a category.

โœ…Verifiably done

You can say yes or no. "Improve performance" is not a milestone.

๐Ÿ”ขFew of them

Three to six per project. Twenty milestones is a task list.

#Milestone or sprint?

They solve different problems and are often confused:

MilestoneSprint
A deliverableA time box
Date set by the outside worldFixed length, repeating
Can span several sprintsAlways the same duration
"v2.0 ships 14 March""Sprint 7, two weeks"

Teams running Scrum use both: sprints for cadence, milestones for the commitments the business made.

#Setting them up

  1. Start from commitments

    List what you have already promised, and to whom. Those are your milestones.

  2. Give each a date and an owner

    An unowned milestone slips quietly.

  3. Assign tasks

    Every task that must be done for that delivery. This is the part that makes a milestone useful โ€” it turns a date into a scope.

  4. Look at what's left

    The gap between remaining work and remaining time is your actual status.

#Tracking

The milestone view shows completion, what is outstanding and what is at risk. Milestones also appear as markers on the Gantt chart.

Milestone progress can mislead

"80% of tasks complete" says little if the remaining 20% is the hard part. Look at which tasks are outstanding, not just how many.

#When one is going to slip

Deal with it early โ€” the options narrow as the date approaches.

  1. Say so as soon as you know

    A month's warning gives options. A day's warning gives excuses.

  2. Separate must-have from nice-to-have

    Most milestones have both. Cutting scope is usually better than moving the date.

  3. Check the critical path

    On Premium, the critical path tells you which delays actually matter.

  4. Move the date if you must โ€” once

    A milestone that moves three times has stopped meaning anything.

#Closing one

When it is delivered, close it. Then look back:

  • Which tasks were missed at planning time?
  • Which estimates were furthest out?
  • What slipped, and why?

That is the input that makes the next milestone's estimate better. Feed it into your project templates.